Introduction
Battery systems are critical subsystems within modern spacecraft. They provide stored energy during eclipse periods, support peak power demands, enable operation before solar-array deployment and maintain essential functions during emergencies or specific manoeuvres. A serious battery failure can reduce mission capability or result in loss of the spacecraft.
ECSS battery qualification testing is the structured process used to generate evidence that a lithium-ion cell, module or battery design can perform against approved requirements in its intended environments with the specified qualification margins. Qualification can involve electrical characterisation, vibration, mechanical shock, thermal-vacuum exposure, life testing, leakage assessment and safety testing.
Within the ECSS framework, battery qualification sits within a wider verification programme. The applicable test levels, durations, sequences, margins and acceptance criteria are not obtained from one document alone. They are derived from the project requirements, mission environment, model philosophy, battery design, customer specification, verification plan and approved tailoring.
Engineers should care because qualification is more than exposing hardware to severe conditions. The evidence must remain representative, traceable and technically defensible. An unsuitable fixture, uncontrolled state of charge, poorly defined pass criterion or incomplete anomaly record can undermine an otherwise successful test.
A robust programme reduces technical risk and supports the customer or design authority in determining whether the battery design has adequate margin for the intended mission.
What Is ECSS Battery Qualification Testing?
Definition
ECSS battery qualification testing is the controlled verification process used to provide evidence that a representative battery design performs in accordance with its approved specifications in the intended environments with the required qualification margins.
Qualification testing focuses on demonstrating the robustness of the battery design rather than assessing the condition of a single deliverable item. Under the conventional ECSS verification philosophy, qualification testing is typically performed on dedicated qualification hardware. A protoflight approach instead subjects flight hardware to qualification-level environments, usually with controlled reductions in test duration, sequence or margin.
Purpose
The principal purpose is to demonstrate that the battery design has sufficient margin to meet defined electrical, environmental, safety and life requirements.
The programme can provide evidence concerning:
-
Electrical capacity and energy.
-
Internal resistance and impedance.
-
Performance after environmental exposure.
-
Structural integrity.
-
Suitability for vacuum and temperature conditions.
-
Long-term degradation.
-
Protective-device behaviour.
-
Leakage and hermeticity.
-
Response to defined fault conditions.
-
Continued ability to satisfy mission requirements.
Qualification testing does not replace design analysis, safety assessment, reliability analysis or system-level verification. It contributes evidence to those activities.
Where It Fits in a Space Programme
Design
Qualification planning supports cell selection, battery architecture, thermal design, structural design, protection philosophy, electrical limits and battery-sizing decisions.
Manufacturing
Production controls and representative qualification hardware help demonstrate that the tested configuration reflects the design intended for manufacture.
Assembly, Integration and Test
Battery health checks, configuration records, handling controls and interface verification support safe integration. Unnecessary use of flight batteries should be minimised during AIT.
Verification
Test specifications, procedures, raw data, test reports, nonconformance records and verification reports contribute to closure of the applicable requirements in the Verification Control Document.
Flight Readiness
Qualification evidence supports customer and design-authority decisions concerning integration and flight readiness. The test laboratory does not independently approve the battery or spacecraft for launch.
Why Is ECSS Battery Qualification Testing Important?
Risk Reduction
Battery qualification can reveal weaknesses that are not apparent during design review or ambient functional testing.
Potential risks include:
-
Capacity loss.
-
Energy loss.
-
Increasing internal resistance.
-
Mechanical damage.
-
Cell movement or connection failure.
-
Electrolyte leakage.
-
Poor low-temperature performance.
-
Thermal-management limitations.
-
Cell imbalance.
-
Protective-device failure.
-
Inadequate life margin.
-
Unsafe response to defined fault conditions.
Testing should be planned to expose relevant risks without creating environments or failure mechanisms that are unrelated to the mission.
Compliance
Qualification testing supports compliance with the approved project requirement baseline.
ECSS standards provide the systems-engineering, verification and testing framework. ECSS-E-HB-20-02A provides non-normative guidance on lithium-ion battery testing. The handbook does not independently create a universal battery qualification requirement.
The controlling position comes from:
-
The business agreement.
-
Project requirements.
-
Invoked ECSS standards.
-
Customer specifications.
-
Approved tailoring.
-
The verification plan.
-
The Verification Control Document.
-
The approved test specification.
Verification Confidence
Objective test evidence provides confidence only when the evidence is controlled.
The programme should establish:
-
The requirement being verified.
-
The verification objective.
-
The test-item configuration.
-
Representativeness of the hardware.
-
Approved environmental levels and margins.
-
State of charge.
-
Electrical operating conditions.
-
Instrumentation and uncertainty.
-
Test sequence.
-
Pass and fail criteria.
-
Anomaly-management rules.
-
Data-retention requirements.
-
Review and closure responsibilities.
Mission Assurance
Battery qualification contributes to confidence that the spacecraft power system can perform during:
-
Pre-launch operations.
-
Launch.
-
Initial deployment.
-
Eclipse periods.
-
Peak power demand.
-
Nominal mission operations.
-
Contingency conditions.
-
End-of-life operation.
Qualification evidence should be considered alongside life-test data, battery-sizing calculations, reliability evidence, supplier information and spacecraft-level verification.
How ECSS Applies to Battery Qualification Testing
Relevant ECSS Documents
Documents that can be relevant include:
-
ECSS-E-ST-10: System-engineering requirements and verification architecture.
-
ECSS-E-ST-10-02: Verification planning, methods, control and evidence.
-
ECSS-E-ST-10-03: Qualification, acceptance and protoflight testing.
-
ECSS-E-ST-10-04: Definition of natural and induced space environments.
-
ECSS-E-ST-20: Electrical and electronic engineering requirements.
-
ECSS-E-HB-20-02A: Lithium-ion battery testing guidance.
-
ECSS-Q-ST-20-08: Storage, handling and transportation of space hardware.
-
ECSS-Q-ST-40: Safety requirements, where applicable.
-
ECSS-Q-ST-20-07: Quality assurance for test centres, where invoked.
-
ECSS-Q-ST-70-02: Thermal-vacuum outgassing screening of materials, where materials-outgassing evidence is genuinely required.
ECSS-Q-ST-70-02 is not a general battery thermal-vacuum qualification standard. Its inclusion should be limited to relevant materials-outgassing requirements.
Handbook Versus Standard
ECSS-E-HB-20-02A is a supporting handbook. It provides guidance, recommendations, recognised test approaches and documentation practices.
It is not a stand-alone qualification standard and does not impose one universal battery test programme.
Qualification, Acceptance and Protoflight
Qualification
Qualification testing demonstrates design adequacy and margin using representative qualification hardware, unless an approved protoflight philosophy applies.
Acceptance
Acceptance testing is performed on deliverable hardware to provide evidence concerning workmanship, condition and compliance with applicable acceptance requirements. It is not a repeat of full qualification.
Protoflight
A protoflight strategy combines aspects of qualification and acceptance on flight hardware. It can reduce hardware and schedule demands but places greater importance on test severity, duration, residual life and risk control.
Tailoring Considerations
Battery qualification should consider:
-
Orbit type.
-
Mission duration.
-
Launch vehicle.
-
Launch loads.
-
Thermal environment.
-
Vacuum environment.
-
Radiation environment.
-
Eclipse profile.
-
Power-demand profile.
-
Battery chemistry.
-
Cell construction.
-
Battery architecture.
-
State of charge.
-
Charge and discharge limits.
-
Qualification model philosophy.
-
Available heritage.
-
Test-item quantities.
-
Destructive-test requirements.
-
Customer and launch-provider requirements.
Tailoring must be documented and approved. It should not be used to remove difficult tests without a defensible technical basis.
Customer Requirements
Customer requirements can supplement, modify or exceed ECSS baselines.
The approved test specification should establish:
-
Applicable requirements.
-
Test levels.
-
Durations.
-
Tolerances.
-
Margins.
-
Test configuration.
-
Operating modes.
-
Instrumentation.
-
Acceptance criteria.
-
Reporting requirements.
-
Witness arrangements.
-
Anomaly and retest rules.
Transport Requirements
UN 38.3 and other transport requirements address the transport of batteries. They do not demonstrate suitability for spacecraft launch loads, mission thermal-vacuum exposure, radiation or operational life.
Transport evidence and space qualification evidence should remain separate and clearly identified.
Typical Battery Qualification Testing Process
Planning
-
Establish the project requirement baseline.
-
Confirm the verification objective.
-
Define the battery architecture.
-
Select the model philosophy.
-
Identify the qualification article.
-
Establish test-item representativeness.
-
Define mission and launch environments.
-
Determine required electrical, environmental, life and safety testing.
-
Define success and failure criteria.
-
Agree the evidence and reporting package.
-
Identify destructive tests requiring separate representative articles.
Preparation
-
Approve the qualification test plan.
-
Approve the test specification and procedure.
-
Confirm test-item configuration.
-
Record cell lot, serial numbers and battery history.
-
Confirm state of charge.
-
Review hazards and emergency controls.
-
Verify fixture design.
-
Confirm electrical interfaces.
-
Define sensor and accelerometer positions.
-
Confirm instrumentation range, accuracy and calibration.
-
Establish data-acquisition requirements.
-
Close Test Readiness Review actions.
Execution
-
Record pre-test inspections and baseline measurements.
-
Apply the approved test sequence.
-
Control state of charge and electrical operating conditions.
-
Monitor voltage, current, temperature and environmental inputs.
-
Conduct functional checks at approved stages.
-
Retain raw data.
-
Record interruptions, deviations and anomalies.
-
Maintain configuration control.
-
Prevent unauthorised changes to the test article or set-up.
Review
-
Compare results with approved criteria.
-
Review achieved levels, tolerances and durations.
-
Assess changes from baseline.
-
Review functional performance.
-
Evaluate anomalies and nonconformances.
-
Confirm whether the test remains representative.
-
Assess the technical basis for retesting.
-
Review all open actions and deviations.
Closure
-
Issue the controlled test report.
-
Include the test configuration and achieved conditions.
-
Provide agreed raw and processed data.
-
Record inspections and functional results.
-
Document nonconformances and dispositions.
-
Close Test Review Board actions.
-
Update the Verification Control Document.
-
Generate the required verification report or evidence package.
-
Record limitations and unresolved matters.
Key Activities
Electrical Characterisation
Electrical characterisation establishes baseline performance and identifies changes after environmental or life testing.
Activities can include:
-
Capacity measurement.
-
Energy measurement.
-
Internal resistance testing.
-
AC impedance measurement.
-
Self-discharge testing.
-
Charge-retention testing.
-
Rate-capability assessment.
-
Cell electromotive-force measurement.
-
Battery magnetic-moment measurement where required.
-
Corona testing for applicable high-voltage battery designs.
Results are meaningful only when the measurement conditions are controlled. Temperature, state of charge, charge method, current, voltage limits, rest periods and previous test history should be recorded.
Environmental Testing
Environmental testing can include:
-
Low-level sine surveys.
-
High-level sine vibration.
-
Random vibration.
-
Mechanical shock.
-
Thermal-vacuum cycling.
-
Electrolyte leak testing.
-
Cell-can hermeticity testing.
-
Radiation testing where required by the mission.
Mechanical testing should use representative interfaces. Where cells or subassemblies are tested in a fixture rather than within the complete battery, the fixture and input levels should account for the intended installation and potential structural amplification.
Battery cells and batteries should not be subjected to an uncontrolled bakeout. ECSS-E-HB-20-02A warns that bakeout can damage the test item.
Life Testing
Life testing can include:
-
Calendar ageing.
-
Constant depth-of-discharge cycling.
-
Constant depth-of-discharged-energy cycling.
-
Mission-profile testing.
-
GEO mission simulation.
-
LEO mission simulation.
-
Real-time testing.
-
Accelerated life testing.
-
Wear-out testing.
Acceleration must be technically justified. Excessive temperature, current or cycling severity can create degradation mechanisms that are not representative of flight.
Safety Testing
Safety testing can include:
-
Overcharge testing.
-
Overdischarge testing.
-
External short-circuit testing.
-
Internal-short-circuit considerations.
-
Vent-pressure testing.
-
Burst-pressure testing.
-
Protective-device verification.
Safety and abuse testing can involve stored energy, fire, venting, electrolyte release, toxic products, explosion and projectile hazards.
Each activity requires a specific technical review, test-facility safety assessment, approved procedure and emergency response arrangement.
Not every listed test is suitable for every assembled battery. Destructive tests may require separate representative articles and controlled sequencing.
Storage, Handling and AIT Controls
Qualification evidence can be undermined by uncontrolled storage or handling.
Controls can include:
-
Storage temperature.
-
Storage state of charge.
-
Shelf-life records.
-
Open-circuit-voltage monitoring.
-
Maintenance charging.
-
Safe handling instructions.
-
Transportation controls.
-
Battery health checks before and after AIT.
-
Minimisation of flight-battery use.
Documentation and Data
The test evidence package should record:
-
Test-item identity.
-
Configuration.
-
Cell lot.
-
State of charge.
-
Test conditions.
-
Fixture.
-
Equipment.
-
Instrumentation.
-
Calibration.
-
Sensor positions.
-
Raw data.
-
Processed data.
-
Functional checks.
-
Deviations.
-
Nonconformances.
-
Analysis.
-
Conclusions.
-
Limitations.
Common Risks and Challenges
Technical Risk
Insufficient design margin can result in capacity loss, structural damage, leakage, increased resistance, thermal instability or premature failure.
A second risk is false confidence. A poorly representative test article can pass without demonstrating the behaviour of the flight configuration.
Schedule Risk
Battery life testing can require months or years. Fixture development, safety reviews, long-duration cycling and anomaly investigation can also affect programme milestones.
Life testing should begin early enough to support design and qualification decisions.
Cost Risk
Qualification hardware, fixtures, instrumentation, specialist facilities and long-duration testing represent significant investment.
Poor planning can cause:
-
Repeat set-ups.
-
Additional test articles.
-
Unnecessary destructive testing.
-
Inconclusive results.
-
Retesting.
-
Programme delay.
Verification Risk
Incomplete coverage can leave critical requirements unresolved.
Common causes include:
-
Missing requirement traceability.
-
Undefined pass criteria.
-
Incorrect test levels.
-
Unrepresentative hardware.
-
Incomplete functional monitoring.
-
Uncontrolled configuration changes.
-
Poorly justified test omissions.
-
Inadequate anomaly disposition.
Documentation Risk
Missing raw data, calibration records, state-of-charge history, sensor locations, battery history or nonconformance dispositions can reduce the value of otherwise valid testing.
Safety Risk
Battery testing can involve fire, explosion, venting, toxic release, electrical shock and stored-energy hazards.
A handbook description or customer test request is not a substitute for the test facility’s safety assessment.
Commercial Claims Risk
Successful testing does not mean the test facility has:
-
Certified ECSS compliance.
-
Approved the battery for flight.
-
Replaced the design authority.
-
Qualified the complete spacecraft.
-
Guaranteed mission life.
-
Demonstrated transport compliance unless the separate transport scope was completed.
Best Practices
Maintain Configuration Control
Ensure that qualification articles accurately represent the approved design.
Record hardware configuration, cell lot, serial numbers, firmware where relevant, interfaces, fixtures, instrumentation and approved changes.
Ensure Requirement Traceability
Link every test objective, condition and pass criterion to an approved requirement or documented verification objective.
Use Suitable and Controlled Test Equipment
Confirm:
-
Equipment range.
-
Calibration status.
-
Measurement accuracy.
-
Measurement uncertainty.
-
Data-acquisition rate.
-
Environmental control.
-
Safety suitability.
-
Fixture compatibility.
Accreditation status depends on the specific method, standard, range and current accredited scope. It should not be assumed for every battery test.
Control State of Charge
State of charge can affect electrical performance, mechanical response, heating and safety behaviour.
Specify, verify and record it at each relevant test stage.
Use Representative Fixtures
The fixture should reproduce the intended mechanical interface without introducing unrealistic resonances, amplification or restraint.
Conduct Independent Reviews
Use Test Readiness Reviews and Test Review Boards to challenge:
-
Requirement coverage.
-
Configuration.
-
Procedure maturity.
-
Safety controls.
-
Instrumentation.
-
Pass criteria.
-
Anomaly dispositions.
-
Evidence quality.
Close Actions Before Progression
Do not advance solely to protect the schedule.
Open anomalies, safety actions and configuration questions should be closed or formally accepted by the authorised project body before the next stage.
Protect Raw Data
Retain raw time-history data alongside processed plots, summaries and conclusions.
Separate Evidence From Interpretation
Clearly distinguish:
-
Measured results.
-
Calculated values.
-
Engineering interpretation.
-
Customer decisions.
-
Unverified assumptions.
-
Remaining limitations.
Related Documentation
Verification Plan
Defines the verification strategy, methods, levels, stages and responsibilities.
Qualification Test Plan
Defines the qualification articles, test sequence, facilities, resources, schedule and review points.
AIT Plan
Defines assembly, integration and test activities within the wider programme.
Test Specification
Defines the requirements, levels, tolerances, margins, conditions and pass criteria.
Test Procedure
Defines the controlled execution steps, measurements, hold points and anomaly responses.
Test Readiness Review Package
Provides the evidence required to demonstrate readiness to begin testing.
Test Report
Records the configuration, execution, achieved conditions, results, analysis, deviations and conclusions.
Verification Control Document
Links requirements to verification methods, planned evidence and closure status.
Verification Report
Assesses the evidence supporting closure of the applicable requirements.
Nonconformance Reports
Record anomalies, technical assessment, disposition and closure.
Requests for Waiver
Record approved departures from applicable requirements where permitted by the project process.
Qualification Status Report
Summarises progress, evidence, open actions, risks and qualification status.
How Success Is Measured
Requirement Compliance
Objective evidence addresses each applicable requirement.
Verification Closure
Planned qualification activities are completed, reviewed and recorded against the correct requirements.
Hardware Integrity
No unacceptable damage, degradation or loss of function occurs, unless the approved test intentionally investigates failure behaviour.
Performance Retention
Capacity, energy, resistance, temperature behaviour and other controlled parameters remain within approved limits.
Environmental Achievement
The approved levels, durations, tolerances and operating conditions are achieved and documented.
Traceability
The relationship between requirement, test article, configuration, procedure, raw data, analysis and conclusion is clear.
Anomaly Closure
Nonconformances, deviations and retest decisions are technically assessed and formally dispositioned.
Flight-Readiness Contribution
The evidence supports the customer or design authority in making an integration or flight-readiness decision.
The laboratory does not independently approve the hardware for launch.
How Resonate Testing Supports Battery Qualification Testing
Planning Support
Resonate Testing can support the translation of customer, mission and environmental requirements into a practical qualification test strategy.
Technical Guidance
Our engineers can review:
-
Test objectives.
-
Environmental profiles.
-
Test-item configuration.
-
Fixture requirements.
-
Instrumentation.
-
Functional monitoring.
-
Test sequence.
-
Data requirements.
-
Reporting expectations.
Test Campaign Development
Resonate can support coordinated vibration, shock, thermal-vacuum and related battery test activity where the agreed scope, equipment capability and safety assessment permit.
Documentation Support
Support can include preparation or review of:
-
Test plans.
-
Test specifications.
-
Test procedures.
-
Test set-up records.
-
Test reports.
-
Data packages.
-
Nonconformance evidence.
Independent Review Support
Independent review can identify:
-
Requirement gaps.
-
Uncontrolled assumptions.
-
Fixture risks.
-
Instrumentation gaps.
-
Safety concerns.
-
Evidence weaknesses.
-
Unrealistic test claims.
Qualification and Flight-Readiness Assistance
Resonate generates controlled test evidence for customer review within the wider qualification and flight-readiness process.
Scope and Claims Boundary
All battery activity is subject to:
-
Technical review.
-
Equipment suitability.
-
Test-item condition.
-
Hazard assessment.
-
Facility safety approval.
-
Schedule and resource availability.
-
Agreed commercial scope.
-
Confirmation of applicable accredited scope.
Resonate Testing does not:
-
Certify batteries as ECSS compliant.
-
Grant flight approval.
-
Replace the customer or design authority.
-
Define the complete project requirement baseline.
-
Guarantee mission life.
-
Provide every battery test listed in ECSS guidance.
Resonate Testing helps customers convert mission and verification requirements into controlled, traceable test evidence.
Your Test Facilitator. Not simply a test facility.
Frequently Asked Questions
What is the difference between qualification and acceptance testing?
Qualification testing demonstrates that a representative design performs against approved requirements with the specified qualification margins.
Acceptance testing provides evidence concerning the condition, workmanship and performance of deliverable flight hardware against the applicable acceptance requirements.
Is battery qualification mandatory under ECSS?
The applicable qualification activities depend on the project requirement baseline, battery criticality, model philosophy, contract and approved tailoring.
ECSS-E-HB-20-02A provides guidance. It does not independently make every listed battery test mandatory.
What environmental tests are normally performed?
Depending on the mission and approved requirements, testing can include sine vibration, random vibration, mechanical shock, thermal vacuum, leakage, hermeticity and radiation assessment.
There is no universal battery qualification profile.
How is compliance demonstrated?
Compliance is demonstrated through traceable evidence against approved requirements. The evidence can include specifications, procedures, configuration records, raw data, test reports, nonconformance records, verification reports and Verification Control Document closure.
Can battery qualification requirements be tailored?
Yes. ECSS requirements are tailored to project characteristics, risk, model philosophy, hardware and mission needs.
Tailoring must be documented, justified and approved.
Does battery qualification include life testing?
Life testing commonly contributes to battery qualification and end-of-life assessment. The exact scope depends on mission duration, operating profile, heritage, battery design and customer requirements.
Is radiation testing required?
It depends on the mission radiation environment, battery design and project requirements.
Radiation evidence may be generated through dedicated testing, analysis, heritage or a combination of methods.
Does UN 38.3 qualify a battery for spaceflight?
No. UN 38.3 addresses transport-related testing. It does not demonstrate suitability for launch vibration, mission thermal vacuum, radiation exposure, spacecraft integration or mission life.
Can cell-level testing qualify a complete battery?
Not automatically.
Integration introduces mechanical restraint, thermal gradients, electrical interconnections, protective devices and cell-to-cell interactions. The verification plan should define which requirements can be addressed at cell, module and complete-battery level.
Can flight hardware be used for qualification?
A protoflight strategy can expose flight hardware to qualification-type testing under an approved model philosophy.
This introduces specific considerations concerning severity, duration, residual life and risk.
Who approves the battery for flight?
The appropriate customer, programme authority or design authority makes the flight-readiness decision.
The test laboratory generates evidence within its agreed scope.
Related Articles
Verification Philosophy
-
Qualification Testing Under ECSS
-
Acceptance Testing Under ECSS
-
Protoflight Testing
-
Space Hardware Model Philosophy
-
EQM, PFM and FM Explained
Battery Testing
-
ECSS-E-HB-20-02A Lithium-Ion Battery Testing
-
Battery Ageing and Life Testing Under ECSS
-
Space Battery Environmental Testing
-
Battery Thermal Vacuum Testing
-
Battery Vibration and Shock Testing
-
Battery Safety and Abuse Testing
-
UN 38.3 Versus Space Qualification Testing
Environmental Testing
-
Vibration Testing Under ECSS
-
Thermal Vacuum Testing Under ECSS
-
Shock Testing Under ECSS
-
Radiation Testing for Space Hardware
-
Environmental Qualification Programmes
Programme and Verification
-
Verification Planning
-
Verification Matrices
-
Verification Evidence
-
Space Qualification Process
-
Verification Control Documents
Reviews and Documentation
-
Test Readiness Reviews
-
Qualification Test Plans
-
AIT Plans
-
Test Specifications
-
Test Procedures
-
Test Reports
-
Nonconformance Management
Plan Your Battery Qualification Programme
Planning a battery qualification programme for a spacecraft, satellite subsystem or space technology demonstrator requires more than selecting tests from a handbook.
The battery design, model philosophy, mission environment, state of charge, fixture, instrumentation, operating profile, safety controls and verification requirements must form one controlled programme.
Resonate Testing provides independent environmental testing, technical guidance and verification support across vibration, shock, thermal vacuum and agreed battery testing activities.
Share your mission requirements, battery information, environmental profiles, model philosophy and verification objectives with our engineering team.
Discuss Your Battery Qualification Programme
Your Test Facilitator. Not simply a test facility.
Recommended internal links
At minimum, connect this page to:
-
ECSS-E-HB-20-02A Lithium-Ion Battery Testing.
-
Battery Ageing and Life Testing Under ECSS.
-
Battery Testing.
-
Space Battery Environmental Testing.
-
Vibration Testing.
-
Shock Testing.
-
Thermal Vacuum Testing.
-
Space Sector.
-
ECSS Knowledge Base.
-
Verification Planning.
-
Contact or Technical Enquiry.
Recommended external references
-
Official ECSS website.
-
Current ECSS standards library.
-
Official ECSS-E-HB-20-02A handbook page.
-
Current UN Manual of Tests and Criteria when discussing UN 38.3.
-
Applicable customer, agency and launch-provider requirements where current and publicly available.
Confirm the controlling editions before linking to specific ECSS standards.